Actions
Bug #13
openEvaluation criteria of the infrastructure
Start date:
08/26/2024
Due date:
09/09/2024 (about 8 months late)
% Done:
0%
Estimated time:
Description
We still need to work with this. Organize a meeting
Schedule after KPMG meeting
Updated by Petri Välisuo 8 months ago
We will make information request to few companies with the price and ask as good setup as possible. Then we use that as a specification for RFQ. Application and concept design can be a guidance for price information.
Who to send it?
- Sofor
- Fujitsu
-
The same applies for Racks, and cooling solutions.
- Rittal
- Orbis
-
Actions