Feature #10
openFeature #3: Submit RFQ for data center
Feature #2: Update Wstar concept plan
Cooling design needs to be updated
Start date:
08/20/2024
Due date:
09/02/2024 (about 8 months late)
% Done:
0%
Estimated time:
Description
Current cooling and heat rejection plan is not ready
- No hot/cold isles, but two racks with closed air circulation and a row cooler
- If heat pump is used, it needs to be connected so that it can be used to simulate all kinds of heat reuse situations
Updated by Petri Välisuo 8 months ago
- Due date changed from 08/26/2024 to 09/02/2024
- Assignee changed from Petri Välisuo to Shiva Sharma
Lets try to solve this together with Hussain and Me