Submit RFQ for data center

Added by Petri Välisuo 9 months ago. Updated 8 months ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/10/2024
Due date:
09/16/2024 (about 8 months late)
% Done:

17%

Estimated time:
(Total: 16:00 h)

Subtasks 8 (6 open2 closed)

Feature #2: Update Wstar concept planNew08/20/202409/16/2024

Actions
Feature #6: Organize meeting with fire safetyNewPetri Välisuo08/20/202409/16/2024

Actions
Feature #7: Update battery storage and DC power feed specificationsNewJohan Dams08/20/202409/02/2024

Actions
Feature #8: Make correct power feed drawingClosedJukka Hautala08/20/202409/02/2024

Actions
Feature #9: Organize a meeting with facility owner and management companyClosedPetri Välisuo08/20/202409/02/2024

Actions
Feature #10: Cooling design needs to be updatedNewShiva Sharma08/20/202409/02/2024

Actions
Feature #4: Finish Wstar collaboration contractNew08/10/202408/30/2024

Actions
Feature #5: Make draft contract for component deliveryNew08/10/202408/30/2024

Actions
Actions #1

Updated by Petri Välisuo 9 months ago

  • Subtask #2 added
Actions #2

Updated by Petri Välisuo 9 months ago

  • Subtask #4 added
Actions #3

Updated by Petri Välisuo 9 months ago

  • Subtask #5 added
Actions #4

Updated by Petri Välisuo 9 months ago

  • Tracker changed from Bug to Feature
Actions #5

Updated by Petri Välisuo 8 months ago

One separate RFQ for wall building, including HVAC, electricity,

Separate RFQ for other parts, with optional packages

- Air to liquid cooling
- Direct to chip cooling
- Direct to chip 2-phase cooling
- Sodium-Ion batteries
- Standard servers and GPUs
- New server architetures, ARM
-

Actions