Actions
Feature #6
openFeature #3: Submit RFQ for data center
Feature #2: Update Wstar concept plan
Organize meeting with fire safety
Start date:
08/20/2024
Due date:
09/16/2024 (about 8 months late)
% Done:
0%
Estimated time:
1:00 h
Description
- Verify with fire safety why is protection class P1 needed in data center space? Is it because we thought there would be LiIon batteries? Can we update that?
- What fire safety is required in the Telecom room which has batteries with different chemistries? Can we mitigate by adding some fire safety cabins or reducing the size of the battery. What is the best compromise?
Actions